Executive Pulse

πŸ’°
Cost Performance Index
1.12
β–² 8% vs baseline
πŸ“ˆ
Schedule Performance Index
0.98
β–Ό 2% behind schedule
⏱️
Forecast Completion
94.2%
β–² On track for Q4
⚠️
Critical Items
3
β–Ό Requires attention

Cost Variance Trend

Export β†’

Schedule Forecast

Export β†’

Control Lab

EVM Analytics Engine

Configure β†’

Monte Carlo Probability

View Details β†’

Risk Scenario Manager

Add Scenario β†’
Risk Probability Impact Status
Material Shortage 35% High Active
Weather Delays 20% Medium Monitored

Operations Hub

Procurement Pipeline

View All β†’
Item Vendor Due Date Status
Steel Beams (500 tons) Acme Steel Co. Dec 15, 2025 On Track
Concrete Mix (200mΒ³) BuildPro Supplies Dec 20, 2025 At Risk
HVAC Equipment Climate Systems Inc. Jan 5, 2026 Delayed

Schedule Tracker

Gantt View β†’

Action Queue

Clear Completed β†’
Action Owner Priority
Review material procurement contract John D. High
Update project schedule baseline Sarah M. Medium
Conduct safety inspection Mike R. Low